Case study · Food packaging plant, 220 people, two shifts
Scrap down to 2.9% on a food packaging line
Most scrap came from changeovers on one line. Standard settings and a first-hour check cut scrap from 4.8% to 2.9% of material by weight.
Result
Scrap as a share of material, by weight
Client
Food packaging plant, 220 people, two shifts
Sector
Manufacturing
Engagement
Program
Period
12 weeks · Apr–Jun 2025
Exhibit 1
Scrap as a share of material, by weight
Source: Scrap weight over material issued, from the production system; eight-week average against the eight weeks before
12 weeks · Apr–Jun 2025
The work

The situation
A plant packing trays for food producers ran two shifts on four lines. Scrap had crept up to nearly five percent of material, and the plant blamed the film supplier.
What we did
Weighed scrap by line and by hour for three weeks. Line 3 produced most of it, and most of that in the first hour after a changeover.
Wrote down the settings the best operators used for each product and put them on a card at the line.
Added a ten-minute first-hour check, run by the operator, with the shift lead signing it off.
Changed the film supplier’s spec only after the line was stable, so we knew which change did what.
The result
Scrap fell from 4.8% to 2.9% of material by weight, comparing the eight weeks after the change with the eight weeks before, from the production system. Line 3 alone went from 7.1% to 3.4%.
What made it stick
The settings cards belong to the operators, who update them when a product changes. The plant manager reviews scrap by line every Monday, not once a quarter.