Case study · Building-products manufacturer, $310M revenue
On-time delivery to 95% at a building-products maker
Sales set delivery dates the plant hadn’t planned. One shared promise date and a daily load plan took on-time delivery from 81% to 95%.
Result
Orders delivered on the promised day
Client
Building-products manufacturer, $310M revenue
Sector
Manufacturing
Engagement
Program and Advisory
Period
12 weeks · Jan–Mar 2025, held through Sep 2025
Exhibit 1
Orders delivered on the promised day
Source: Orders delivered on the date in the order confirmation, from the transport system, monthly
12 weeks · Jan–Mar 2025, held through Sep 2025
The work

The situation
A maker of wall panels and trusses promised dates that its plant hadn’t planned for. One order in five arrived late, and contractors had started ordering early to be safe, which made the plan worse.
What we did
Built one promise date from the production plan and truck capacity, shown to sales when they quote.
Started a fifteen-minute daily load meeting between the plant, transport and customer service.
Called the twenty largest contractors to explain the new dates and ask them to stop ordering early.
The result
Orders delivered on the confirmed day went from 81% to 95% over twelve weeks, from the transport system. Six months of Advisory later, it was still 94–96% each month.
What made it stick
Sales can’t confirm a date the plan doesn’t have, and the daily meeting has its own fifteen-minute agenda that doesn’t need us.