Note

When a plant tells us scrap is a supplier problem, we ask to weigh it by the hour for two weeks.
In most plants we visit, the first hour after a changeover runs at more than twice the scrap rate of the hours after it. The settings aren’t written down, so each operator finds them again, and the material pays for it.
The fix is unglamorous: a card at the line with the settings the best operators use, and a ten-minute check in the first hour. In the packaging plant in our case studies, that took scrap from 4.8% to 2.9% of material by weight.